Phone: (734) 429-4907 Hours: M-F 8:30am-5pm

One of America's Best Places to Live, Work and Play

Navigation

Parking Lot #4 Paving Project

NOTIFICATION –PARKING LOT #4 PAVING PROJECT

FROM:      Gary Roubal, City Superintendent/Engineer, City of Saline DATE:        September 22, 2017

RE:              FALL PHASE OF THE 2017 PAVING PROJECTS

PROJECT LIMITS:   Entire Parking Lot #4 from entrance on US-12 to entrance on W. Henry

 

The City of Saline is utilizing TIFA Funds for the following project work:

  • Milling/resurfacing of  some existing bituminous  pavement
  • Removal of some pavement/subgrade and replacement with aggregate base and pavement
  • Repair of miscellaneous sidewalk and concrete curb
  • Replace pavement markings

Sections of the parking lot will be closed for period of time to complete the various types of drainage, concrete, and asphalt paving work.  Closures will be kept to a minimum as much as possible.  Barricades, barrels, and other devices will be utilized to conduct the milling, removals, limestone base, and paving work, and for the safety of workers and the general public.

The City has contracted with D. N. Higgins of Ann Arbor, together with their subcontractors, to perform the construction work. Midwestern Consulting of Ann Arbor will perform much of the construction inspection and monitoring of the project activities. Both firms have at least 25 years of extensive experience working on various projects in the Saline Community

Residents and stakeholders are encouraged to contact the City Engineer at 734-429-8296 ext 2222 if: (Note: During the period of October 5 thru Oct 13 contact the Saline DPW at 429-5624)

  1. You would like to discuss the construction activities in more detail
  2. You have any specific questions or need to discuss any transportation or delivery coordination needs
  3. You have any particular operational concerns with any of the proposed construction activities

THE CONTRACTOR HAS PROVIDED THE BELOW TENTATIVE SCHEDULE TO PERFORM THE PROJECT WORK

Estimated Work Period         (Weather permitting):

  • Sept 28  to Oct 5           Start-up,  removal & replacement of miscellaneous concrete
  • Oct 9 to Oct 16              Mill/remove pavement; underdrain; place aggregate base;
  • Oct 17 to Oct 18            Placing new asphalt pavement
  • Oct 19 to Oct 23            Place signs, parking blocks, pavement markings; perform clean-up

PLEASE NOTE THE FOLLOWING PROJECT ACTIVITIES:

  • Do not park vehicles in the parking lot during the above dates and during the construction activities. The contractor will make all efforts to expedite the work so that the lot may be completed in shorter time.
  • Contact the City Engineer, DPW Director, or project inspector on site if you need to schedule a time for any specific deliveries to adjacent businesses.
  • For afterhours emergencies involve during or after the project work hours, please contact the Saline Police Dispatch at 429-7911.

We apologize for any inconveniences during the construction period, including dust, mud, noise and vibration. Our goal is to respond to the needs of the affected property owners throughout the construction period.